St. John’s Church in Bergen – rehabilitation 2024-29

St. John's Church has significant rehabilitation needs, and the ongoing work ensures that the church will be universally accessible, more environmentally friendly and preserved for the future. Read about the work we are doing here.

These pictures shows some of the work being done in february 2025. We are currently drilling for waterborne heating.

We apologize for the noise

The work will occasionally cause noise, especially during the daytime. We apologize for any inconvenience this may cause to the neighborhood and hope for your understanding. The goal is to preserve the church's authentic expression while adapting it for the future with universal accessibility and environmentally friendly solutions.

Extra noise due to well drilling

In connection with the installation of waterborne heating, there will be work that may cause increased noise during this period:

Period: February 10, 2025 – April 7, 2025
Working hours: Monday – Friday, 07:00–17:00
Type of work: Well drilling

We are doing our best to reduce noise during the quietest hours. Do you have any questions or experience any problems? Please contact us.

 

Timeline for the Work 

The rehabilitation of St. John's Church follows a planned timeline with clear milestones, but in such rehabilitation projects, adjustments are always needed along the way. 

2023 – Preparations Begin 

  • Scaffolding and coverings are set up around the bell tower to prevent stones from falling. 

 

2024 – Work Begins 

  • Safety scaffolding is converted to working scaffolding. 
  • Official opening: On November 18, Minister Kjersti Toppe and City Councilor Reidar Digranes open the work (press clip from NRK). 
  • Interior concrete is removed to allow the walls to dry. 
  • Preparation for waterborne heating under the church. 

 

2025 – Full Scale Scaffolding and Start in the Tower 

  • The rig area is established. The entire tower is covered with scaffolding. 
  • Heaters will be replaced with radiators, and waterborne heating will be completed. 
  • Work on the roof and tower begins, including copper and sheet metal work, masonry, and glass work. 

 

2026 – Focus on Tower, Nave, and Choir 

  • Roof work, masonry, and glass work continue throughout the church, with particular focus on the tower, nave, and choir. 

 

2027 – Completion of the Tower

Work on the tower is completed, and the scaffolding is taken down. 

  • Work on the nave and choir continues. 

 

2028 – Focus on the Interior 

  • Work on the nave and choir continues. 
  • Interior upgrades begin, with universal design, floor rehabilitation, new accessible toilets, modern lighting, and updated sound and power systems. 

 

2029 – Rehabilitation Completed 

  • St. John's Church enters a new era, with improved functionality and preserved historical soul. 

 

Rehabilitation for the Future  

St. John's Church has significant rehabilitation needs, and the ongoing work ensures that the church will be: 

  • Universally accessible – for everyone, regardless of ability. 
  • More environmentally friendly – with modern heating and better energy solutions. 
  • Preserved for the future – as a safe and beautiful setting for faith, culture, and community.  

Beklager, men vi kan ikke finne din posisjon pga instillingene i nettleseren din. Du må tillate autolokasjon for å kunne benytte denne funksjonaliteten:

Se instruksjoner for din nettlester under:

Internet explorer

Internet options / Privacy / Location / klikk på "Clear sites"

Chrome

Settings / Advanced / Priacy and security / Content settings / Location -> Fjern "kirken.no" fra blokkert-lista

Firefox

Options / søk etter "location" / settings / Fjern "Kirken.no" fra blokkert

Safari

Settings for this website / Location -> "Allow"